NeuConnect
| NeuConnect Interconnector | |
|---|---|
Map of NeuConnect Interconnector  | |
| Location | |
| Country | Germany, United Kingdom | 
| General direction | east-west | 
| From | Germany | 
| Passes through | North Sea | 
| To | England | 
| Construction information | |
| Expected | 2023 | 
| Technical information | |
| Type | submarine cable | 
| Type of current | HVDC | 
| Total length | 725 km (450 mi) | 
| Power rating | 1,400 MW | 
| AC voltage | 380 kV GER/400 kV UK | 
| DC voltage | 525 kV | 
NeuConnect is a high-voltage direct current submarine power cable under construction since 2023 between the Isle of Grain, England and Wilhelmshaven Germany, expected to operate in 2028. It will be the first interconnector between the UK and Germany. The cost of £2.4 billion (€2.8 billion) is financed by Meridiam from France, Allianz Capital Partners from Germany, Kansai Electric Power Company from Japan, and Tokyo Electric Power Company from Japan. The Chair of NeuConnect is Julia Prescot CBE.